- Site utility piping
- Piping and instrumentation diagram
- Brine water inlet and outlet
- Storm water treatment
|
|
One portion of this project included
brine water inlet and outlet, potable water inlet,
desalination water and storm water piping for a new
desalination plant. General arrangement and site utility
drawings were prepared.
Axiom Engineers(sm) reviewed and
revised the package desalination plant’s
process and instrumentation diagram specifying
all piping material and design piping details.
The project also consisted of the relocation,
modernization, and upgrade of the storm water
treatment systems to remove oily residues. Axiom
Engineers(sm) prepared general arrangement, site
utility, piping, and instrumentation drawings
for permitting and construction.
|